T024 - Statewide Improvement Plan - Fairmount Commuter Rail
| Project | FY2013 State Bond Cap  | 
FY2013 Project- Financed  | 
FY2013 Federal Funds  | 
FY2013 Other Funds  | 
FY2013 Total  | 
|---|---|---|---|---|---|
| Statewide Improvement Plan - Fairmount Commuter Rail | 
11,156,000 | 0 | 0 | 0 | 11,156,000 | 
This project upgrades two rail stations, reconstructs six bridges, constructs a new track interlocking switching system and upgrades the existing signal system.
Location: Hyde Park
 top of page