FY2018 - FY2022 Capital Investment Plan
B396 - East Brookfield Court - Exterior & HVAC Repairs Budget Recommendations

Project
FY2018
State
Bond
Cap

FY2018
Special
Obligation
Bond

FY2018
 
Project
Financed

FY2018
 
 
Federal

FY2018
 
Other
Contributions

FY2018
 
 
Total
East Brookfield Court - Exterior & HVAC Repairs
 
3,000,000 0 0 0 0 3,000,000

Study, design, and construction for major repair work to address HVAC and water infiltration. The roof will be replaced, ground water infiltration will be addressed, and some of the HVAC equipment will be replaced.

Location: East Brookfield